Supertech twin towers demolition on August 28: Know the detailed process of razing down Noida's iconic building

Credit: DNA- Published on August 18, 2022
A whopping 3,500 kg of explosives will be filled in 9,400 strategically dug holes to safely bring down the 100-meter-tall structures.

You are here


💡 newsR Knowledge: Other News Mentions

Noida

Metropolis in Uttar Pradesh, India
Noida Authority also directed Edifice that the work of removal from the site should be started from September 29.
Credit: DNA - Published 4 days ago

The fresh stir comes nearly two months after Shrikant Tyagi was caught on camera assaulting and abusing a woman resident of the society.
Credit: DNA - Published 5 days ago

Tyagi community has demanded that the Authority provide the list of persons who bulldozed Anu Tyagi's house.
Credit: DNA - Published 6 days ago


Related videos from verified sources

Supertech might build residential property over twin tower rubble | Oneindia News *News 01:53
Credit: Oneindia - Published on September 4, 2022 


Noida Supertech Twin Towers: After demolition, cleaning of debris is underway | Oneindia News*News 01:27
Credit: Oneindia - Published on August 29, 2022 


Noida Supertech Twin Tower demolished successfully, no damage reported | Oneindia news *News 02:12
Credit: Oneindia - Published on August 28, 2022 


Related news from verified sources

A whopping 3,500 kg of explosives will be filled in 9,400 strategically dug holes to safely bring down the 100-meter-tall structures.
on August 18, 2022 • DNA

The Supertech Twin Towers are set to be demolished on August 21 through a highly planned and intricate process, using massive-scale explosives.
on August 3, 2022 • DNA

Noida Supertech Twin Towers' demolition would leave behind about 35,000 cubic metres of debris that would take at least three months to be cleared.
on August 26, 2022 • DNA

You might like